Lafitte Greenway DPW Status Update - February 4, 2015
The City of New Orleans Department of Public Works issued the following status update on February 4, 2015.
Placement of the asphalt portion of the Lafitte Greenway bicycle and pedestrian path is 75% complete in Areas 2, 3, 4, and 5. The Department of Public Works construction contractor, Durr Heavy Construction, has completed installing most of the trail lighting fixtures in Areas 2, 3, and 4, and continues installation of trail lighting in Area 5. Lighting wiring will be installed toward the end of the project construction, when the project is ready for public use.
Read moreFOLC Member Happy Hour Tonight at Finn McCool's
Join FOLC in kicking off the Lafitte Greenway's opening year with a happy hour celebration this Thursday, Jan 29, at Finn McCool's Irish Pub. Meet your fellow riders, rollers, and Greenway supporters. FOLC Members receive a complimentary specialty cocktail, thanks to our hosts at Finn McCool's!
City to Begin Making Improvements to S. Jefferson Davis Bike Path
The below announcement was issued by the City of New Orleans Department of Public Works.
The Department of Public Works’ construction contractor, Hard Rock Construction, will begin improving portions of the Jefferson Davis Parkway Bicycle and Pedestrian Path between Gravier St. and Orleans Ave. on Tuesday, January 27, 2015.
Read moreFriends of Lafitte Corridor Elects Six New Members to its Board of Directors
FOR IMMEDIATE RELEASE
NEW ORLEANS, LA, January 27, 2015— Friends of Lafitte Corridor (FOLC) today announced the election of six new members to its Board of Directors. The new board members include: Amy Allen, Clarence Becknell, Judith Dangerfield, John Hopper, Eric Van Hoven, and Jared Zeller.
"We are delighted to welcome this extraordinary group of individuals to the Friends of Lafitte Corridor's board of directors," said Annalisa Kelly, Interim Chair. "Their wide array of expertise and talent further strengthens FOLC as we retool the organization to serve as the community's partner in the long-term maintenance, programming, and use of the Lafitte Greenway."
DPW Issues Latest Greenway Update – Jan 8 2015
Construction Update from City of New Orleans Department of Public Works, January 8, 2015
Placement of the asphalt portion of the Lafitte Greenway bicycle and pedestrian path is 75% complete in Areas 2, 3, 4, and 5. The Department of Public Works construction contractor, Durr Heavy Construction, has completed installing most of the trail lighting fixtures in Areas 2, 3, and 4, and continues installation of trail lighting in Area 5. Lighting wiring will be installed toward the end of the project construction, when the project is ready for public use.
Read moreAerial Images of the Greenway's Progress

Craig Guillot of NOLA Aerials captured extraordinary aerial low-altitude images of Lafitte Greenway on October 20, 2014. Construction of the Greenway is over 50% complete in these images, shot from two locations--North Prier and Jefferson Davis Parkway.
Read moreGreenway Community Garden and Market Planning to Receive Federal Support

Friends of Lafitte Corridor is proud to announce that we have been selected by the White House and six federal agencies to participate in Local Foods, Local Places, a federal initiative providing technical support to 26 communities nationwide to integrate local food systems into community economic action plans. A team of agricultural, transportation, environmental, public health and regional economic experts will work directly with Friends of Lafitte Corridor and a team of community partners to bring together growers, stakeholders, Lafitte Corridor neighbors and City leaders to develop a plan for community gardens and a farmers market on the Lafitte Greenway.
Read moreNew Orleans gets a boost in its "bicycle-friendly" ranking
The League of American Bicyclists recently upgraded New Orleans from bronze to silver bicycle friendliness ranking, thanks largely to a significant increase in new bike lanes and the upcoming Lafitte Greenway!
Read moreMCNO's Anti-Crime Camera Program
The Mid-City Neighborhood Organization is supporting the installation of anti-crime cameras on Mid-City Neighborhood homes. MCNO received a $9,500 grant from the Mid-City Security District to make the security camera program possible. This is a great opportunity to promote safety in the Lafitte Corridor! If you live in Mid-City in the Lafitte Corridor, consider applying to MCNO’s reimbursement program to install a camera on your home. For more information and to apply, visit MCNO’s website.
Greenway Progress Update: November 2014
Laffite Greenway Status: Nov. 26, 2014
FOLC thanks Cheryn Robles and everyone at DPW for another monthly greenway construction update:
————–
Placement of the asphalt portion of the Lafitte Greenway bicycle and pedestrian path is now 75% complete in Areas 2, 3, 4, and 5. The Department of Public Works construction contractor, Durr Heavy Construction, has completed installing most of the trail lighting fixtures in Areas 2, 3, and 4, and continues installation of trail lighting in Area 5. Lighting wiring will be installed toward the end of the project construction, when the project is ready for public use.